Press release: City adding stop signs

Over the next several months the City of Clovis Public Works Department will be installing stop signs in the area located between Seventh Street and 14th Street and Cameo Street and Thornton Street. The signs are being installed to provide control at previously unmarked intersections. In order to keep with a uniform approach to the […]

Year in review: City ends busy year with re-opening of Hull overpass

le7uav-le7ua01230yirhullstreet.jpg

The Hull Street Overpass re-opened in November, signaling the end of 28 month of frustration for many Clovis residents. Kevin Wilson More than $3 million and 254 tons of steel. Thousands of vehicle pass-overs per day. And sighs of relief throughout south Clovis. The re-opening of the Hull Street Overpass in early November was one […]

Press release: Hull Street overpass ribbon cutting Wednesday

The City of Clovis will be holding a ribbon cutting on the north side of the Hull Street Overpass at 11:00 a.m., Wednesday, December 1st, 2010. The ribbon cutting will be immediately followed by a reception at Our Lady of Guadalupe at 108 N. Davis Street when area representatives involved with the reconstruction will comment […]

Hull Street Bridge open to traffic

lc5i5o-lc5i231120hullstoverpassopen2.jpg

Freedom New Mexico: Tony Bullocks Clovis City Engineer Justin Howalt drags a road closed sign off the Hull Street overpass Friday just before the opening of the overpass. Kevin Wilson “First motorcycle,” the crew exclaimed at 10:52 a.m. as a grey-haired main pulled up to Justin Howalt and asked if it was safe to pass. […]

Hull Street overpass close to completion

CNJ staff Crews are putting the final touches on the Hull Street overpass, with hopes that cars could cross the new structure as soon as Friday. City Engineer Justin Howalt said the final step is a pedestrian fence, a standard feature with the sidewalk area overlooking the railroad. The fence could take up to two […]

Weekly update — Oct. 17

Opening ceremony scheduled for overpass A ceremony for the opening of the Hull Street Overpass will be coming in November, but likely long after the first car passes over the new structure. “We’re hoping to start laying asphalt at the end of next week,” City Engineer Justin Howalt said. The target completion date is Nov. […]

City commission gets Hull Street overpass update

Kevin Wilson A short Clovis City Commission meeting had its share of history, spiritual events and music to go with a Hull Street Bridge update. City Commissioner Bobby Sandoval told commissioners and audience members Thursday that cement pouring, which started Tuesday night, is finished on the overpass, which was closed in June 2008 for safety […]

Press release: Night work will be performed on Hull overpass

Hamon Contractors, Inc. will be performing night time operations to pour the bridge deck on the Hull Street Overpass. The pours will be on September 7th and 9th and will run from approximately 8 p.m. to 6 a.m. During the course of the pour overhead lighting will be used. The need for the night time […]

Weather slows overpass progress

CNJ staff Recent winter weather has slowed progress of the replacement of the Hull Street Overpass. City Engineer Justin Howalt said the target date for the overpass is now November. Howalt said the plan this week is to work on drilling for the bridge’s foundation. The step involves drilling 70-foot holes, and filling them with […]

Hull overpass named one of top priorities for city

kwh4v2-117citygoalshome1.jpg

CNJ staff photo: Tony Bullocks Raymundo Garcia of Plains Masonry in Clovis saws a brick Friday for the masonry work on a home under construction in the Raintree subdivision in northeast Clovis. Getting affordable housing is among the top five priorities for Clovis this year, City Manager Joe Thomas has said. By Thomas Garcia: Freedom […]